top of page

FLS Library

FLS Group Logo with Tagline _ Color_edited.png

PELICAN POINT POWER PLANT PROJECT 2/2

Updated: Jan 15


Volume: 28 packages, 3,779 cbm, 341. MT

Origin: Dung Quat, Vietnam

Port of Discharge:Adelaide, Australia

FinalDestination: Pelican Point Combined Cycle Power Plant

Challenges: 

•Complexity due to the cargo’s size with max length 15.46M, width 9.55M, height 5.30M

•The nearest BBK terminal at the POD to the job site is not workable

•Investigate suitable direction to the job site, adjust construction to fit the cargo during transportation

--> We got involved in the discussions at a very early stage, which allowed the client to design and fabricate up to the absolute maximum dimensions.

--> Coordination with carrier for special berthing at RO-RO/ Cruise ship terminal


Scope:

•Apply for a special permit in order to berth at the RO-RO/ cruise terminal.

•Traffic management survey in Australia

•Vessel berthed at a RO-RO/ Cruise ship berth

•Cargo unlashing discharge operation, supervision by FLS PM

•Due to cargo dimensions, FLS had to remove fencing and widen the gate at the port

•Traffic lights, traffic signs had to be removed during the trucking from port to the jobsite

•Police escorted our trucks and stopped the traffic when necessary



Back
bottom of page